The Feasibility of Dredging Road of Gwadar Port, Pakistan
Time:Jan 28,2021Hits:Hits:-

2015.12~2016.9

The proposed road starts from the access road of Guadar Port, runs to north along the east beach and turns to the inner land parallel to the airport road, ends at the junction of Makran Coastal Highway. The total length is 18.9 Km. Two-way 4-lanes pavement and 6-lanes subgrade of expressway standard will be adopted. Recently the pavement of 4 lanes will be built and will be expanded to 6 lanes by 2026, the design speed is 100Km/h. One grade separation with length of 58 m will be built, the each side of the bridge will be 15.64m wide and gap of left and right sides is 20 mm. 48 new R.C.C box girder culverts will be built.